Tyler ISD 2004 Bond
Board Update
February 20, 2007
· A & E Consultants
A. EHRC Architects are providing Construction Administration
services throughout the project duration for Jack/Douglas/Peete.
B. Fitzpatrick Butler/PBK, Architects (FB/PBK) are providing Construction Administration services throughout the project duration for Austin/Bonner.
· Construction Projects
A. Douglas Elementary School-New Construction
a. Work Completed
All structural steel erection is complete (exclude colonnade).
All drywall and plumbing & electrical rough-ins, duct work main runs, fire sprinkler mains and ceramic tile are complete in the two story wing and one story classroom wing. Painting is approximately 60% complete in the two story and one story classroom wings.
Brick work is approximately 65% complete.
b. Work in Progress
Structural steel erection is underway at the colonnade. Drywall framing, HVAC duct work, plumbing & electrical rough-ins, fire sprinkler mains continue at the Gym/Music Room/Cafetorium. Painting continues as well as acoustical ceiling grid. Millwork is being installed at both two story and one story classroom wings.
c. 3-Week Look Ahead
Work items mentioned above will continue. Dirt work for concrete paving is under way.
d. Comments
Douglas is ahead of schedule, at this point, and under budget.
C. Austin Elementary School-New Construction
a. Work Completed
Building concrete work and structural steel are complete. The dome frame and metal deck are complete (metal roof is not installed). 100% of the roof is dried-in and all mansard framing is complete. Drywall framing is complete. Sheetrock is approximately 90% complete. The dock at Kitchen is complete. Brick work is approximately 55% complete. The roof is 100% dried in.
a. Work in Progress
Miscellaneous steel work at the main entry is underway. Finish roof sheeting and flashing is in progress. The brick work continues on the east and south sides of the building. In addition, above ceiling rough-in for plumbing, electrical, ductwork for HVAC and fire protection continues. Tape and bed of sheetrock is underway.
b. 3-Week Look Ahead
The work items listed above will continue.
c. Comments
RPR is on schedule and on budget.
D. Bonner Elementary School-New School
a. Work Completed
Building concrete work is complete as well as the structural steel. Retaining wall is complete. All CMU work is complete. The roof is 100% dried in. Drywall framing is approximately 80% complete.
b. Work in Progress
Miscellaneous steel work at roof mansard continues. Roofing finish sheeting and flashing is underway. Brickwork continues on the north and east side of the building. In addition, wall and above ceiling rough-in for plumbing, electrical, duct work for HVAC and fire protection continue. Drywall framing continues as well as hanging of sheetrock on the second floor classroom wing.
c. 3-Week Look Ahead
Work items listed above will continue.
d. .Comments
Bonner is on schedule and on budget. The retaining wall has revealed cracking of the Keystone at the large radius section. We have the engineer of record as well as the testing lab and a third party structural engineer looking into the structural integrity of the wall. It could be the end of April before a final decision can be determined.
E. Peete Elementary School-New School
a. Work Completed
Approximately 90% of the storm drainage is complete.
Except for the Kitchen, all concrete footings are complete. The CMU foundation is approximately 90% complete.
b. Work In Progress
Concrete footings at Kitchen, storm drainage, underground rough-in for plumbing and electrical are in progress. The retaining wall work has commenced at the south end of the property.
c. 3-Week Look Ahead
The items listed above will continue.
d. Comments
Rain has caused approximately two weeks of delay. Denson will make up the rain delay.
END