Board Approves Agreement for Assessment and Master Planning of District Facilities

Board of Trustees approved the agreement with Corgan Associates, Inc. in the amount of $65,000.00 for Assessment and Master Planning of district facilities.  Funding will be provided from the Bond funds.

As part of the district’s ongoing assessment of facilities needs and conditions, the Administration is requesting the services of Corgan Associates, Inc. be retained. The architects would provide a district-wide assessment of facilities, administration master planning, as well as organizational and departmental assessment services.


Facilities Department Provides Update on Construction Projects

Tyler ISD Construction Project Manager, Monte Robinette, provided the Board of Trustees an update on the progress of the school construction projects. 

 

Orr Elementary School

All building slabs are complete; structural steel erection started and the installation of decking on second floor is underway

Clarkston Elementary School

Roofing installation has started; brick work has started in court yard area.  Ductwork and all above ceiling work is underway; framing for interior and exterior walls is started; structural steel erection is nearing completion with only the gym, and one other area remaining.

Woods Elementary School

Structural steel erection started on June 22, 2009; final building slab pour is scheduled for the week of July 27, 2009.  Foundations and underground electrical and plumbing are complete in all areas.

Jones/Boshears School

Building slabs for several areas are complete.  The parking lot for the administrative area has been poured; the second floor slab pour on Jones is scheduled for week of July 27, 2009.  Steel erection for two areas is complete and erection for another area has started.

The metal building for the arena has been delivered to site, with the erection to start next week.

 

 

###